Monthly Report #10
EXECUTIVE SUMMARY

          
During the month of August the following significant construction activities have been achieved:

  • Placement of concrete over closed up floor openings on the second and third floors continues; 
  • Continued erection of structural steel;
  • Placement of the new foundation walls on the south and southeast elevations;
  • Placement of concrete infills at Slab on Grade over MEPS sub slab installations continues;
  • Continued cutting of the existing slab on grade in order to install the new MEPS under slab work.
  • Renovation work in the existing Performing Arts Center (PAC) continues;
  • MEPS Trade contractors continue to install hangers from the ceiling to support their future work;
  • Spray fire proofing continues on the second floor and has begun on the first floor;
  • Installation of the new ductwork and chilled water piping begun this period;
  • Installation of  new storm water waste lines within Beacon Hall begun this period;
  • Installation of electrical conduits begun this period;
  • Installation of new sanitary lines begun within Beacon Hall this period

During the month of September the following significant construction activities will commence:

  • Completion of concrete slab infills over underground utilities within the Beacon building;
  • Completion of the erection of Structural Steel at the West and East additions;
  • Continued installation of hanger assemblies to support future mechanical and electrical systems;
  • Completion of the roofing system at the second floor south wing;
  • Continued installation of the new MEPS through out the Beacon Building;
  • Completion of the renovation work in the Performing Arts Center.
  • Continuation of exterior and interior masonry work;
  • Continuation of exterior cold formed metal framing.

Newfield has updated the Construction Schedule for the Beacon building with a data date of August 14, 2007.  The schedule for the Performing Arts Center has not been updated from the last data date. However, as of the end of the month, the construction is on target based on the schedules.

The Construction Administrator continues to meet throughout the month with the Project Team chairing the Owner’s Meetings and participating in the General Contractor’s Subcontractor Coordination Meetings.

 